Shortly after Colonel Lilley’s response to the State of North Carolina’s request for the original Grainger Labs analytical data sheets for TTHM testing, the base collected samples for December 1983’s TTHM testing and sent them into Grainger Lab. The Hadnot Point WTP and the Naval Hospital’s Emergency room sink were among the areas tested. The results were available in January 1984. Once again Bruce Babson noted that there was something interfering with the testing on
his report. From past experience we know that it was PCE and TCE and it was in all four samples taken from Hadnot Point, including the Naval Hospital’s emergency room sink.
The Confirmation phase of the NACIP program kicked off in April 1984 with a meeting at Camp Lejeune between the Navy’s contractor, Environmental Science Engineering (ESE), located in Gainesville Florida and Navy/USMC officials from LantDiv and Camp Lejeune. In May 1984 a
Work and Safety Plan detailing what tasks the scientists were requested to perform for the Confirmation Study was issued. The purpose of their work was to determine whether specific toxic and hazardous materials identified in the 1983 Initial Assessment Study (IAS) were present on the base in concentrations considered to be hazardous. The contractor was required to provide LantDiv with a monthly progress report due by the 15th of each month. The final well samples were schedule to be collected by 7 July. Then by 3 August, ESE would complete their evaluation of the testing results and then complete their draft report by 27 August. The final report was scheduled to be completed and presented to LantDiv and the Marine Corps by10 September 1984.
On 7 June 1984, the base newspaper carried an article titled
“Environmental Study kicks-off.” The article was meant to be an informative piece to allay any fears which may arise from the presence of ESE personnel collecting samples and drilling throughout the base. Colonel Lilley was quoted in the article “While contractor personnel will routinely wear personal protective equipment such as chemical resistant coveralls, we do not expect to expose anyone to any contaminants.” The article also read that the results of the survey were expected by August 1984.
What the Marine Corps failed to tell the readers of this article was that they were already exposed to the very contaminants the ESE scientist were looking for and the Marine Corps and LantDiv already knew the contamination was in the base’s drinking water system as early as
October 1980. The Corps did nothing to protect or warn them from the danger posed by the contamination in the drinking water aboard the base.
Personnel aboard the base were completely unaware they were in any danger and as far as they knew, their Corps was looking out for them and protecting them from a possible problem which may or may not even exist. Semper Fidelis?
Even the most carefully laid plans are subject to unforeseen events which can completely disrupt their goals. Sometime during the month of June, the
EPA published a proposed Recommended Maximum Containment Level (RCML) for TCE and PCE in drinking water. The Federal Registry Notice contended that “VOCs are man made chemicals; their presence may indicate that a pollution incident has occurred.” Now the cat was out of the bag. To make matters worse, “The EPA has determined that human exposures to certain VOCs via drinking water may have an adverse effect upon the health of persons, thereby warranting regulatory action.” Camp Lejeune’s drinking water problem would soon be on the State’s “radar”.
With a few clicks of a type writer, the EPA interjected a crisis into the NACIP program for Camp Lejeune. To make matters worse, the announcement came right in the middle of their contractor’s groundwater sampling of the base. A collective breath was drawn and held in LantDiv and in certain offices of the base. The one bright spot in the announcement was there was no provision requiring the Navy/USMC to report the VOC contamination to the State of North Carolina, despite the fact they already knew VOCs were present in the base’s potable water supply. For now, their terrible secret was safe.
Throughout the months of June and July 1984, ESE proceeded to sample the various monitoring and potable water wells in and around the 22 sites identified as possibly hazardous by the 1983 IAS for Camp Lejeune. On 6 July, ESE sampled the wells around
Site 22, the Hadnot Point Fuel Farm. Among the wells sampled was Hadnot Point water supply well number 602 (HP 602). The samples were packed in ice and sent to ESE’s lab in Gainesville Florida. A week later, as scheduled in the Work and Safety Plan, the
third progress report arrived at LantDiv from ESE. The report was directed to the Engineer in Charge, Jerry Wallmeyer, and advised him that ESE had collected their samples but there would be a two week delay in completion of the project due to problems with filters on some of the monitoring wells for the last round of sampling. The field investigation was scheduled for completion on 4 August.
Then suddenly, the document trail ceases from August 1984 through November 30th 1984. We have been unable to locate any of the remaining ESE progress reports, draft report or final report as mentioned in the Work and Safety Plan. Unfortunately, ESE’s
document warehouse suffered an extensive fire in January of 1999 and the building was destroyed along its historical records. This fire occurred a month before officials at LantDiv spent four weeks turning their archives upside down looking for the mysterious
10 May 1983 Wallmeyer letter. From other documents, we have determined this letter was an action plan from LantDiv to locate, characterize and remediate the VOC problem on the base. Note, this action plan was crafted two years before the VOC problem was revealed to the EPA, the State of North Carolina and personnel aboard the base.
What we do have is ESE’s January 1985,
Evaluation of Data report. Deep within this report is a set of data values and conclusions for the 6 July 1984 Site 22 Samples at the Hadnot Point Fuel Farm. Among the chemicals found in well HP 602 was benzene at 380 ppb and toluene at 10 ppb. These two VOCs are components of fuel and indicated fuel contamination of the groundwater had occurred. ESE notes in their
report: “Of extreme importance is the high level of benzene (380 ug/l) detected in the sample collected from the deep water supply well No. 602. This benzene concentration far exceeds the 10 minus 5 human health risk limit of 6.6 ug/l; therefore the use of this well should be discontinued immediately.”
According to the official Marine Corps Time line well HP 602 was shut down on 30 November 1984 after results for a sample taken by the NACIP Program were received. A sample taken on 3 December 1984 indicated well HP 602 was contaminated with benzene at 121 ppb, TCE 1,600 ppb, DCE 630 ppb and PCE at 24 ppb. Ironically, there is no mention of ESE’s prior sample for well HP 602 on 6 July 1984. There is no mention of this sample (6 July 1984) or the benzene results from the December 1984 sample in the current version of the
USMC’s time line. The ESE 6 July 1984 sample does not appear in any prior USMC public statement. According to the Marine Corps, they discovered well HP602 was contaminated with VOCs (note the use of benzene is avoided). Furthermore ESE’s July sample indicated only trace amounts of the organic solvents PCE, TCE and DCE were present. The December LantDiv sample also revealed that a large plume of organic solvents was located in the vicinity of well HP 602. This new plume had nothing to do with the plume containing fuel products emanating from the tank farm. .
The critical question is why did it take four months for the Marine Corps to shut down the highly contaminated well HP 602 after it was documented as contaminated? What about the other wells on the base? What about the warnings from the Army lab, Jenning’s Lab and Grainger Lab between October 1980 through January 1984? What about Bruce Babson’s
August 1982 findings that the well fields for Tarawa Terrace and Hadnot Point were the respective sources for those system’s contamination? What about
BUMED 6240.3B or C, why were they not followed? Well HP 602 was located adjacent to the fuel farm since it was constructed in 1941! According to the strict language found within the BUMED, well HP 602 and many of the other wells which were later found to be contaminated aboard the base, were unfit for use and thus should not have been allowed to provide water to their respective water treatment plants.
How many lives could have been saved if the Navy and the USMC had simply followed their own regulations in place since 1963?
Where are the missing progress reports from ESE? There is no doubt that the July 6th samples would have been known by August 15th, the next progress report. That report is missing. Judging from the conclusions stated in the
Evaluation of Data report, there is no doubt that ESE warned LantDiv and Jerry Wallmeyer that something was terribly wrong with well HP 602 and if well HP 602 was contaminated, what else was out there?
The cover up was now in full swing and the worst was yet to come.
Semper Fi?
Mike Partain